vendredi 6 mars 2015

ERICSSON Node B Commissioning and Integration

Node B Commissioning and Integration

1        Preparation
1.1         Laptop with the below software installed
1.2         Cable and accessories
1.3         Node B Scripts and License
1.4         Test Phone
2        Node B Commissioning Process Summary
3        Node B Commissioning
3.1         Format DUW
3.2         Transfer the Basic software package to NodeB
3.3         Restart Node B with basic software
3.4         Run Cabinet Equipment Wizard
3.5         Run OAM Wizard
3.6         Run Site Equipment Configuration
3.7         Run Iub Transport script
3.8         Activating Integration Unlock
3.9         Run HS/EUL script
3.10       Changing the RUW power to 60 Watts
3.11       Installation of the License Key File
3.12       Creation of Configuration Version.

1.     Preparation

This section mentions the software and test tools required to do the RBS integration.
1.1.           Laptop with the below software installed                     
                                           1.  Tera Term Version 4.61
2.  Filezilla 3.2.2.1(FTP Client) or any other FTP client
3.  FileZilla Server Version 0.9.31(FTP Server)
4.  RBS Element Manager P7
5.  Java1.6.0_14jre-6u14-windows-i586-s
6.  RBS 6000 Basic Software P7.1.6
1.2.           Cable and accessories                                  
1.      Serial to RJ45 cable
2.      USB to Serial Adaptor
3.      LAN cable
Total of 7 integration scripts are used during the RBS integration.        
1_Cabinet.xml
2_OAM.xml
3_Site_Equipment.xml
4_Iub_Scripts.mo
5_HS_EUL_Parameters.mo
The license file/integration unlock is mandatory. Without the license/ file or integration unlock the
5_ HS_EUL_Parameters.mo cannot be run successfully.

Any phone which is capable of the displaying the cell information (eg: TEMS, Phones with Netmon)

2.     Node B Commissioning Process Summary


2.1.           Format DUW
2.2.           Install Basic package P7.1.6
2.3.           Restart the Node B in the basic software
2.4.           Run Cabinet Equipment Wizard
2.5.           Run OAM Wizard
2.6.           Run Site Equipment wizard
2.7.           Run Iub_Scripts.mo Script
2.8.           Activate integration unlock
2.9.           Run HS_EUL_Parameters.mo Script
2.10.       Changing the RUW power to 60 Watts
2.11.        Installing the license key file
2.12.       Creating a Configuration Version.

3.     Node B Commissioning

This section explains in detail the steps mentioned in the previous section.
Connect the serial cable to the LMT A port of DUW and run Tera Term software.
Make sure that you see the command prompt $



Put  the Node B in BackUp mode, by issuing the following command.
reload—
We can check the directories within the NodeB by issuing
vols



Since the /c2 is not automatically mounted, we will have to manually mount the drive by issuing the following command.
mount_c2
vols






Now we will proceed with the formatting of the hard drives /c2 and /d. The commands to do
the format is given below.
formathd /c2
                  formathd /d



Once the format is done, reload the RBS. After this is done, we again move to the back up mode to start the configuration. This is done by issuing a reload – command


The next step is to proceed with setting the IP address in the nodeB. The command issued is
ifconfig le0 169.254.1.1 netmask 255.255.0.0



Set the IP address in your laptop to 169.254.1.2.
Make sure that you set the Default gateway IP address in the laptop without which the integration scripts will fail.



3.2.           Transfer the Basic software package to NodeB.
Open an FTP client such as Filezilla and connect to the RBS IP address 169.254.1.1 through LMT B port of DUW


Make sure you select the root directory ‘/’ at the RBS side.
Transfer /c2 and /d directories to the RBS as shown below.


Once the transfer is completed make sure the size of /c2 is 129M and /d is 39M. This can be done by issuing the vols command



3.3.           Restart Node B with basic software

Now we have to restart the RBS with the basic software. The command to be issued is
reload. Wait till the RBS restart is completed



We login to the RBS using the element manager software. The local maintenance  IP address of the RBS 6201 is always 169.254.1.1.


Checking the Finger print
This section shows a series of screenshots on how to check the finger print of the RBS. The finger print is used to generate the license key file for the RBS.



3.4.           Run Cabinet Equipment Wizard 
The RBS is configured with the cabinet type when we run the Cabinet equipment wizard. Also some basic sector and IP definitions are done in the Cabinet equipment configuration. The script to be run is 1_Cabinet.xml.
From the tools menu, select Cabinet Equipment configuration. We can choose the wizard or the scripts option. Since cabinet equipment configuration is quite simple, we will be running the wizard manually. Please follow the screenshots below.


Click Next


Since we are running the wizard manually click Next. The RBS will proceed with a restart and it is a normal behaviour. Wait for the restart to complete.

Once the restart is completed, you will see a screen as mentioned below. Click Next

In the next screen you will select the RBS cabinet type, key in the cabinet information and select the Radio Building blocks for the sectors. We will be using the radio building block RBB12_1A. In this example we will be configuring two sectors. Click next once done.

In the next page you will see the power supply and the battery configuration. Key in the number of PSU’s and the battery backup in Ampere Hour if applicable. Click next once done.

The next page shows the Local maintenance IP address and the subnet mask. The default IP address for the RBS is 169.254.1.1 and netmask is 255.255.0.0. Click next once done.

Please confirm the parameters and select the option to restart the RBS after cabinet equipment configuration.

Observe in the Teraterm that the RBS is starting up in the Initial CV


3.5.           Run OAM Wizard 
Now that the Cabinet equipment configuration is completed, we will run the 2_OAM_Script.xml through the OAM Access Configuration Wizard. This will configure OAM IP address, the OAM VLAN, the OAM Gateway , OAM Subnet mask, the Iub IP address(User Plane/ Control Plane IP), the Iub VLAN, the Iub Gateway and the Iub subnet mask. In addition to this we will also define the server IP addresses specific to Singtel.
To run the OAM wizard, from the tools menu select OAM access configuration.

You will see the screen below.

Since we will be using the 2_OAM_Script.xml select Use Configuration file and browse the file from the folder where the OAM file is stored.

Once the current configuration is loaded, click next.
            The following screens show the parameters that have been defined through our scripts.
This screen shows the Local Maintenance IP address and the subnet mask.
The next screen shows the OAM IP, OAM VLAN, OAM Gateway and OAM subnet mask configuration. Also we select the Transmission type (TNB). TNB is used for Optical Gigabit Ethernet through SFP and is required for IPRAN sites.
This screen shows the Iub IP address, Iub VLan, Iub Gateway,Iub Subnet mask and the IP Sync Ref IP addresses.

The next screen shows the next HOP IP address which s required for OAM access. The next hop IP address will be the OAM Gateway IP address.


The next screen shows the Server configuration inside the Singtel network and they are standard values. Click next once done.
                        The next screen shows the NTP servers for the time setting in the RBS.

            The next screen shows the Network Synchronization available. We have configured two IP Sync Ref’s in the RBS. Therefore we will see 2 entries here.

                        Confirm the parameters that have been entered in the OAM script. Click Finish





3.6.           Run Site Equipment Configuration
The next step is to run the Site Equipment configuration. We will be running 3_Site_Equipment_script.xml.
The site equipment configuration defines the site name, number of carriers/sector, defines the external equipment such as ASC, and the feeder cable settings.
To invoke the Site equipment configuration, go to Tools à Site Equipment configuration.

Select the Site equipment file 3_Site_Equipment.xml and
Click next

This screen shows the Site name and the logical name.







The next screen shows the SAU and the PSU configuration. SAU is currently used only for the 6102 sites.

The next screen shows the Sector Data info including the latitude and longitude.

The next screen shows the Carrier configuration on per sector basis.
The next screen shows the ASC configuration.
The next screen defined the band at which the RU’s will operate.
                        The next screen shows the Antenna feeder configuration.

The following screen shows the parameter numhscoderesources and numeulresources. Set the parameters according to the requirement.
Confirm the parameters in the next screen by clicking Finish.
Once the Site Equipment configuration is done, you will see the following screen.
3.7.           Run Iub Transport script
Now we will proceed to run the 6_Iub_script.mo. This will define the Iub link towards the RNC
From the tools menu select Run Command file
From the screen below select the Iub script by clicking Browse.

Make sure you select “Halt on Errors” and Verbose logging” before clicking the Start button.


Once completed you will see the following messages.



3.8.           Activating Integration Unlock
We assume that during RBS integration, we do not have the License Key file. In the event of not having the LKF, we can activate a feature called “Integration Unlock”. This feature is conceptually similar to the “Emergency Unlock” feature. All the RBS software and hardware licenses will be available for a maximum period of 7 days. The advantage of the feature is that we need to touch the Emergency Unlock feature this reserving it for emergency purposed and at the same time have the same functionality.
                     The command to activate integration unlock (to be done at Teraterm) is
                     $ license iu activate
                     The command to check the status of Integration unlock (to be done at Teraterm) is
                     $ license iu status
                     Please see the screenshots below for details.

3.9.           Run HS/EUL script
This script is required for the HS/EUL features to work properly. It is an .mo script and to run it go to Tools à Run Command file
                      Browse for the HS/EUL script.


Click on “Halt on Errors” and “Verbose Logging” and click Start. You should

 3.10.           Changing the RUW power to 60 Watts
Most of Singtel RBS sites require that the each carrier supports 30 Watts. Since we have configured 2 carriers per RUW, we will have to set the total power of RUW to 60 Watts. Thus each carrier will have a power of 30 Watts.
                     We will have to set the power for all the RUW’s in the RBS.
                     From the MOM view in the Element Managed, browse to the following path
ManagedElement -> Equipment->RbsSubrack->RbsSlot-> AuxPlugInUnit>RruDeviceGroup->TpaDeviceSet->TpaDevice

In the MO properties window set
Click on Apply to confirm the settings.


3.11.           Installation of the License Key File
                     After obtaining the License Key File, we will be proceed with LKF installation.
                     Open the FTP server software in your laptop(such as Filezilla Server)
                      Click on the Users icon
                     Select the folder where the license key file is installed.
                      Once the selection of the folder is done, click OK
In the Element Manager go to Licensing View. Go to MO properties and select “Update LicenseKey File”.
Now in the following page, key in the following details of the FTP Server(our Laptop). Username, Password, IP address and the License File Name. It is shown in the screen shot below.


Once all the details are keyed in clock on “Execute”.

3.12.           Creation of Configuration Version.
                     Before proceeding with the creation of CV make sure that there are no alarms in the RBS.

 To create the CV, go to Software view in the Element Manager.

Go to the CV tab.
 Click on Create CV. You will see the following window.
Once the CV name and the operator comments are keyed in click Create.

Make sure that the created CV is visible in the CV list. If it is not click refresh. Set the CV to startable and restart the RBS with the CV.


49 commentaires:

  1. Réponses
    1. Field Maintenance Experience Sharing: Ericsson Node B Commissioning And Integration >>>>> Download Now

      >>>>> Download Full

      Field Maintenance Experience Sharing: Ericsson Node B Commissioning And Integration >>>>> Download LINK

      >>>>> Download Now

      Field Maintenance Experience Sharing: Ericsson Node B Commissioning And Integration >>>>> Download Full

      >>>>> Download LINK VY

      Supprimer
    2. Field Maintenance Experience Sharing: Ericsson Node B Commissioning And Integration >>>>> Download Now

      >>>>> Download Full

      Field Maintenance Experience Sharing: Ericsson Node B Commissioning And Integration >>>>> Download LINK

      >>>>> Download Now

      Field Maintenance Experience Sharing: Ericsson Node B Commissioning And Integration >>>>> Download Full

      >>>>> Download LINK jj

      Supprimer
  2. Thanks a lot for sharing this...

    RépondreSupprimer
  3. thanks for all, you are the best.

    RépondreSupprimer
  4. Nice... thanks.

    HOW MOUNT C2 IN DUS 4102 ???. the comand $mount_c2 not found.

    RépondreSupprimer
    Réponses
    1. $
      $reload --
      $pboot set pa stand_alone_du 1
      $pboot sabe pa
      $reload --

      ..................WAIT TIME.... esperar 30 segundos Aprox.
      $mount_c2
      $formathd /d
      $y
      $formathd /c2
      $y
      ifconfig 169.254.1.1 netmask 255.255.0.0

      Supprimer
  5. how can i download all this, please share on nastotech@gmail.com

    RépondreSupprimer
  6. Thanks very much for the sharing please can you send it in challu2014@gmail.com I want to download

    RépondreSupprimer
  7. plzz share on my email :-hussainarshad456@gmail.com

    RépondreSupprimer
  8. hello how to change password with Element Manager

    RépondreSupprimer
  9. plzz share on my email :arsengishyan@mail.ru

    RépondreSupprimer
  10. Please share to cstrand@swiftel-bmu.com

    RépondreSupprimer
  11. How can I configure the RNC RBS? How can I restart only a cell on the RNC?
    Kindly share it by sending to my email: Sibaka1234@gmail.com

    RépondreSupprimer
  12. please share to kenroyn@gmail.com

    RépondreSupprimer
  13. Plz share at abhishekjohnsaini@gmail.com

    RépondreSupprimer
  14. Plz share at abhishekjohnsaini@gmail.com

    RépondreSupprimer
  15. Hi guys, How to add new sector in DUS and DUW plz. is someone know the MODOP plz.thks

    RépondreSupprimer
  16. Plz share at amirhesam.momeni@gmail.com

    RépondreSupprimer
  17. hi pliz share me confguration alarm in the duw aitouyahiasofiane@gmail.com

    RépondreSupprimer
  18. Pls thank you very much. Pls how do we resolved NTP reachability alarm and system clock alarm Duw. Pls will to download the information you have shared .pls you send it my Joezorro@gmail.com

    RépondreSupprimer
    Réponses
    1. hi kenneth
      i have the same problem about ntp server reachability fault , can you help me on this issue

      Supprimer
  19. please share on my email suleman_btk@yahoo.com

    RépondreSupprimer
  20. Hello! Tell me, please, how to update the software RBS 6601.
    oknotlt@gmail.com

    RépondreSupprimer
  21. Hi, Can i have the softwares ? Thanks in advance

    ni.alpr@gmail.com

    RépondreSupprimer
  22. Cable db9 rj45 shema de connection

    RépondreSupprimer
    Réponses
    1. See link below
      https://kb.fortinet.com/kb/viewContent.do?externalId=11344

      Supprimer
  23. hello which q 'one knows where I can get the free software please thanks in advance

    RépondreSupprimer
  24. Hello guys,
    Could you pls send me the software packet P7.1.6 ? ntn2410.free@gmail.com is my email address.
    Thanks very much.

    RépondreSupprimer
  25. Very informative and useful historical post. I see you have a lot of other cool stuff available at your website, simply bookmarking it to check in spare time. Thanks and keep the good work up.

    Press brakes

    RépondreSupprimer
  26. Hi Dear,

    I Like Your Blog Very Much. I see Daily Your Blog, is A Very Useful For me.

    You can also Find Top sync licensing companies Music Mill is one of the top sync licensing companies in Australia, NZ and Asia. We work with producers to negotiate music synchronizaton sync licences for use in advertising campaigns.

    Visit Now:- https://www.musicmill.com.au/licensing/

    RépondreSupprimer
  27. Réponses
    1. At out area, licenses are injected by the RNC guys, sorry.,🤨🧐😒😒😤

      Supprimer
  28. How to make cable db9 rj45 DUW3101

    RépondreSupprimer
  29. Hello please share to my mail tyhamah@gmail.com

    RépondreSupprimer
  30. El Yucateco Hotels & Casinos - MapYRO
    El Yucateco 오산 출장마사지 Hotels 원주 출장안마 & Casinos 광주 출장마사지 - 제주 출장샵 Casinos, 화성 출장샵 Resorts & Hotels in San Francisco, CA Find your perfect spot for the ultimate in Mexican cuisine.

    RépondreSupprimer
  31. Field Maintenance Experience Sharing: Ericsson Node B Commissioning And Integration >>>>> Download Now

    >>>>> Download Full

    Field Maintenance Experience Sharing: Ericsson Node B Commissioning And Integration >>>>> Download LINK

    >>>>> Download Now

    Field Maintenance Experience Sharing: Ericsson Node B Commissioning And Integration >>>>> Download Full

    >>>>> Download LINK

    RépondreSupprimer
  32. Field Maintenance Experience Sharing: Ericsson Node B Commissioning And Integration >>>>> Download Now

    >>>>> Download Full

    Field Maintenance Experience Sharing: Ericsson Node B Commissioning And Integration >>>>> Download LINK